Ruby Collins Construction
4806 Wright Rd
Smyrna, GA 30082

Marta Medical Center Station

 

Project: Marta Medical Center Station (HVAC, Plumbing, Fire Protection)
Completed July 1996

Description: Peachtree Mechanical Inc. was awarded the Marta project located at Northside Medical Center. We provided all services to install the complete HVAC, plumbing and fire protection systems. This project included the tunnel exhaust system that consisted of setting three 10 foot diameter exhaust fans. This portion of work made the headlines in the Mechanical Contractors Association of America cover page.